TLC provided a full package 180m dam decommission in Westmare Lake Watershed near Summerland, BC.
Services included:
- - Environmental assessment of the site
- - Initial dam assessment
- - Survey with using conventional total station
- - Hydrological and hydraulic study of the dam
- - Providing Decommissioning Plan
- - Providing Rehabilitation Plan
- - Providing Environmental Management Plan (EMP)
- - Providing Environmental Monitoring and Construction Conformance.
All deliveries were completed on time and on budget to the client satisfaction.